Time and Material Tickets a GC Can Check and Sign

A time and material ticket is the piece of paper that turns “just do it and we’ll figure it out” into money. I’ve rejected so many of them that I lost count. Most of those subs did the work. They just couldn’t show it.

I worked the tinner trade for about four years, and I’ve been in construction more than twenty years. Now I manage projects for a general contractor in Salt Lake, and I review subcontractor change orders every week. I never filled out a T&M ticket when I was a tinner. I read a lot of them now.

This post is written from the GC side. The examples are ductwork because that’s my trade, but it works for any sub who does extra work on a ticket.

What is a time and material ticket?

A time and material ticket, or T&M ticket, is a daily record of extra work. It lists the people, the hours, the material and the equipment that went into work that isn’t in your contract. The super signs it, and it later becomes the backup for a change order.

The ticket comes after the work. That’s why everything that happens before you start matters so much.

Before you start, get it in writing

When a super says “just do it,” here’s what I want to see that same day:

  • A written message from the super that says what was agreed to in the field.
  • A rough order of magnitude (ROM) from the sub. That’s a rough cost, so everybody knows about how big this is before the work starts.
  • The same message seen by both sides, the super and the sub.

Then I usually call the sub’s PM and we talk through what it is.

Field changes shouldn’t be GC-driven. If the change is going to get paid by the owner, it should come from the owner. That can be an RFI response, an owner change directive, an ASI, an owner proposal request (PR) or a bulletin. If it’s a design change, get confirmation from the architect and the owner.

If it’s something between two subs, whatever gets worked out in the field gets coordinated with the office, usually the PMs, and we come to an agreement in writing.

Who should sign your time and material ticket

The super. That’s the only GC signature that should be on it. If there’s no super on the job, or the PM is filling in, the PM can sign. If you are working directly with an owner, they need to sign it.

What you want is a triangle of accountability. The sub’s foreman or PM signs. The GC super signs. The GC PM reviews. Those three should be one team looking at the same piece of paper.

If you are working directly with an owner, you are two sides of that triangle and need to be accountable for what is on the tickets. The good, you get to present your cost in an offer and acceptance format. The bad, if you miss the mark on costs, that is what you are getting paid.

Get the time and material ticket signed the same day

A T&M ticket should be signed by the super on the day of the work.

If it shows up next week, I ask for the labor report with descriptions to back it up. If it isn’t from the last few days, I get really skeptical. On my jobs the contract usually gives three days to turn in a ticket, with the hours documented.

Some subs are great at this. Some don’t know how much it matters, or they’re overworked and struggle to get them in on time. Either way, a late ticket is a harder ticket to approve.

Whether your contract has a deadline, and what it is, depends on your contract. Read it. I’m not a lawyer, and this is not legal advice.

What a signature on a time and material ticket means

It comes down to the fine print, and whose fine print it is.

The companies I’ve worked for have a policy, and for good reason. We don’t sign a sub’s T&M form. We only sign our own, so we control the fine print. Our ticket has a line that says the super is verifying that work happened and that is paper, not committing to an increase.

When we sign, we’re saying we know this is different from the base scope and we’re willing to talk about it later. It is not a guarantee the ticket gets paid. It means we’re willing to negotiate.

If a super signs a sub’s form, he may be agreeing to terms he won’t like. That’s why the companies I’ve worked for won’t.

What gets a ticket rejected

These are the things I’ve rejected tickets for, or crossed out:

  • No project name or no location.
  • Hours that don’t match the daily logs.
  • One person on standard time and overtime that adds up to more than 12 hours in one day.
  • Base scope hours, or work on items that were already in the original contract.
  • Manager time.
  • More than one foreman on the same shift, or something like it.

Sometimes a super signs a ticket just to get it done, without reviewing everything on it. That can cause confusion later.

Standard, overtime and premium time

This is the one I argue about most.

  • Standard time is hours on work that isn’t part of the original contract, at your standard rate. If you haven’t worked out your own rate, start there.
  • Overtime is hours above and beyond standard shift hours on that changed scope, at your overtime rate (typically, time and half but not always).
  • Premium time is the difference between your overtime rate and your standard rate.

Premium time comes up when we ask a sub to speed up. Say we ask you to work extra hours to get base scope done sooner. The first 8 hours are base scope, and that work is already in your contract. The extra hours are base scope too, just worked on overtime. Because the work is still inside your allotted hours, we only pay the premium, the difference between standard and overtime.

Subs don’t like premium time. It’s still fair to the owner and to the GC, because the base scope is already in the contract.

How a time and material ticket becomes a change order

The sub takes the tickets back to the office. The PM, or whoever writes the change orders, puts them together and sends them in. If you can price the change before you start instead, do that. I went through how to price an HVAC change order.

A change request built from T&M tickets should always have:

  • The signed T&M tickets.
  • A drawing showing what changed.
  • A clear description that shows the scope is real and where it is.
  • Photos with markups.

A vague description, or a missing location, is a red flag. Annotated photos of the work, the reason and the problem are really appreciated, and they speed up a review.

I once got a photo with no markings and a question, “Does that look right?” It was an open door with the hardware on it. I said it looked fine. He sent back a laughing emoji. I said that wasn’t a joke. Then he resent it showing the hand trim on backwards, keeping the door from latching. I felt a little silly. But I’m not going to spend time on something that isn’t clear. Be clear about what you’re showing and what you want answered, and it’s easier for me to answer.

Photos that back up the ticket

  • Take one wide shot and one close-up, and make sure they capture the problem.
  • Draw on the photo to show the area. Bluebeam works, or mark it up right on your phone or tablet.
  • Send a short write-up with it, and ask your question if you need an answer.

A photo with “fix this” under it does nothing for me.

What to say

My rules don’t change. Nothing gets agreed out loud. Don’t start until the work and the rough cost are in writing.

When the super says “just do it”: “I can do that. Can you text or email me what we agreed to? I’ll send you a rough number before we start.”

At the end of the day: “Here’s today’s ticket for [location]. The hours match our daily report. Can you sign it before you leave?”

When you send the change: “Attached are the signed T&M tickets for [dates], the marked-up drawing and photos of [location]. The question we need answered is [question].”


Keep them in the field for quick use

The Change Log Template will help you keep track of what is extra. The Field Extras Starter Sheet is one page. It has the checklist I’d run before saying yes to any extra, how to figure your floor price in three lines, and what to say when somebody wants a number on the spot. It’s free.


Common questions

What is a time and material ticket?

A daily record of the people, hours, material and equipment used on work that isn’t in your contract. The super signs it, and it becomes backup for a change order.

Who should sign a T&M ticket on the GC side?

The super. If there’s no super, or the PM is filling in, the PM can sign. The GC PM then reviews it.

Does a signed T&M ticket mean the GC agreed to pay?

Not on my jobs. A signature on our form means the super saw the paper and knows it’s different from base scope. The price still gets negotiated. What a signature means on your job depends on whose form it is and what your contract says.

How soon does a T&M ticket need to be signed?

The day of the work. On my jobs the contract usually allows three days to turn it in. After that, expect questions.

What is premium time in construction?

The difference between the overtime rate and the standard rate. It gets paid when a sub works overtime to speed up base scope that’s already in their contract.